New old town paving

The paved areas throughout the old town were redesigned following the excavation work to renew the pipe infrastructure.

This page was translated automatically. The City of Innsbruck assumes no responsibility for the accuracy of the translation.
Blick auf das Vier-Viecher-Eck mit dem neuen, hellen Pflaster

New old town paving at Vier-Viecher-Eck© Stadt Innsbruck/RS

Redesign of the paved areas in Innsbruck's old town centre

The renewal of the pipeline infrastructure in 2020/21 was followed by the comprehensive redesign of the paved surfaces in Innsbruck's old town. Areas less affected by the excavation work were repaired, while the remaining areas were completely renewed. The work was carried out in two construction phases between April 2024 and July 2025. A total of 7,500 square metres of the old town was repaved, including Herzog-Friedrich-Straße, Hofgasse, Pfarrgasse, Schlossergasse, Kiebachgasse and Seilergasse. The construction process was planned in such a way that businesses, restaurants, events and pedestrian traffic could continue to operate with as little disruption as possible.

Design principle

The basic principle for the new paving is a non-directional laying of Luserna gneiss in a passé bond, with six different stone sizes. The design by architects ARGE Köberl-Giner-Wucherer creates a harmonious overall impression in harmony with the conical streets and squares as well as the existing historical surfaces. The precise laying with steel templates ensures a uniform appearance. The unbound construction method also enables the sustainable reuse of the stones for future excavations as well as improved retention and a cooling effect due to the water absorption of the joints. The basis for the realisation was the close cooperation between the city's specialist departments, in particular City Department Urban planning, mobility and integration and City Department Civil engineering, and the ongoing involvement of the expert advisory board for the City and Townscape Protection Act and the Federal Monuments Office.

Additional measures to improve quality

In addition to the new paving, the quality of life in the old town centre was also improved. New trees on Mundingplatz, at Vier-Viecher-Eck and in Herzog-Otto-Straße bring additional greenery to the historic surroundings. A drinking fountain at Vier-Viecher-Eck invites visitors to linger and refresh themselves, while new infrastructure shafts make it easier to organise events. The installation of bollards at the Ottoburg and Marktgraben entrances has also enabled safety standards to be adapted to current requirements. New benches make a significant contribution to enhancing the consumer-free experience in the old town. In addition, the lighting situation at selected entrances to the old town was improved.

State

The paving work has been completed.

Participation

The paving work was accompanied by a dialog process. Several information events gave the public the opportunity to find out about the construction project and ask questions.

In the run-up to the project, the operators of the guest gardens were informed in individual meetings about the upcoming work and the associated restrictions. In addition, local business owners were given the opportunity to speak directly to the construction company and employees of the City of Innsbruck at a separate information event and to voice their concerns.

During the construction phase, a separate construction office was set up in the old town, which served as a direct point of contact for the population and businesses. Every week there was the opportunity to raise concerns in person and discuss them directly.

Costs

The total costs for the surface design in the historic city centre amounted to 8.9 million euros. After deducting the reimbursement amounts to be paid by the pipeline operators and the subsidies from the Municipal Investment Programme 2023, the City of Innsbruck's expenditure amounted to 4.7 million euros.

Contact

Opening hours

Office:
Monday through Friday:
8.00-12.00 and by appointment

Phone:
Monday to Thursday:
8.00-12.00 and 13.00-16.00

Friday:
8.00-12.00

Opening hours

Office:
Monday through Friday:
8.00-10.00 and by appointment

Phone:
Monday to Thursday:
8.00-12.00 and 13.00-16.00

Friday:
8.00-12.00